Progress of works on Plac Małachowskiego’s construction site

Apr 17 2013

In the office building, acquired by KSP in the middle of the last year, main construction works commenced in October 2012.

In the 7-storey historical part of the building structural enabling works are almost completed and structural elements on the ground floor are in progress. The main works in this part of the building include: strengthening of the existing construction, realization of new lift/installation shafts as well as  new structural elements are being executed with new floor slabs.

In the new 6-storey part of the building underground parking and basement structural works are completed and the main structural works have reached the +4 level with the vertical members well advanced on the fourth floor. The extension will increase the total area more than 5 000 sqm.

Historic nature of the project determines conservator’s restrictions and requirements on the protection of the existing building’s façade and parts of its interiors. Thanks to the cooperation with conservator a historical façade from Plac Małachowskiego and Traugutta Street will be reconstructed.

Kulczyk Silverstein Properties, investor and owner of the building,  cooperates with Hochtief Development Poland which acts as Developer. Warbud S.A. is General Contractor.

The renovation and development project is expected to be completed in the 3rd Quarter 2014.